Crawl Space UP
Home BACK First Floor Second Floor

Constructing the Crawl Space - foundation - Subfloor
March 26, 2004

Son Josh and I cut and mounted the sill plates.  I also had to mount a nailing rim joist on both ends and extra nailers across each door opening.  Note we had the garage covered with a tarp to protect supplies and have a solid cement floor to work on.


Starting Joists
The first thing to do to start the building was set the support beams onto the footing pads blocked up to the bottom of the floor joists, then the floor joists, then inspection, then floor decking, then walls.  After setting the sill plates I rechecked for square and then level.  These two items will battle me the rest of the say up to the roof.  I was 1/8" off square and had both an 1/8th to high and an 1/8th to low in some wall sections for a total of 1/4" of adjustment.  Not bad.

Josh helped me get started with the floor joists. 


Underfloor beams & Shear Wall
Josh was only able to get me started.  Turned out they didn't deliver all the angle joist hangars we needed for the Bay Wall section, so Josh and I concentrated on getting the key joists in place to determine exact height of the 6 beams under the joists.
We also built the small Shear wall that will run from the footing up to the roof trusses. 

The Joists were as 25' up to 32' long.  They also sold us the higher weight baring joists which just sort of continues the "overbuilding" that the house is getting.


Finished floor joists w/first logs laid in place
I was able to finish off the joists myself.  For their size, these 30' I-Joists are surprisingly light.

I needed to start picking out the first logs to go down on the Sill plate.  These needed to be as long as possible and also the best strength condition.  Not easy to find in the sizes I wanted.


Peeking at laser level in crawlspace
Once I had the first perimeter of logs laid down (not bolted down yet), I need to check my log height all around the perimeter. I used my rotating laser level, set up in the crawl space to point 1/4" from the top of my starting spot.  Then, all I had to do was rotate the laser around and take measurements around the perimeter.

Joists in and readied with first logs
I had to shim some logs here and there, then again, I had to plan down a few log sections, but all in all I was able to decrease the difference in level for this first course of logs to about an 1/8" overall.   I also had to start protecting the Cedar from rain.  This quickly became quite a challenge.

Greg & I laying subfloor
Mid May '04 I found a builder friend  named Greg to help with some work now and again.  He came over to help say the floor decking against the first layer of logs.  The 3/4"T&G went down real easy.  We had to have half the first course of logs off so we could butt the first course of floor decking into it and had to have the last edge without logs so we could measure/cut the floor to size.  Had I laid all the logs the last row of flooring would not have been  able to lay into place.

Once we had the floor down we could really start laying logs in earnest.

Greg stayed on with me through the completion of the project.  Greg became a main leading figure in the construction process.

See the "First  Floor" link at top to continue

Email to:  Dulane or Roy - Remove *** from address - Copy/Paste into your email program:  ***webmaster@spiderhollow.com***
SpiderHollow Sing Log Building project:
 Lot purchase '97.  Permitted 8/20/03 Ground breaking 8/30/03 Move in 9/20/05

"Man did not weave the web of life -- he is merely a strand in it.
Whatever he does to the web, he does to himself."

~ Chief Seattle, 1854 ~