
Gravel carefully spread all around the drainage pipe

White fabric to keep silt from filling up rocks, and then the pipe. |
January 9th, 2004
One of the parts I felt comfortable doing was the foundation
drainage. Had to dig a trench all around the footing to lay perforated
4" drain pipe. It had to all flow down hill to the 1 exit spot on one end of
the foundation. From that one exit spot the 4" drain pipe extended
about 15' from the foundation till it day lighted into the yard.
Sounds
easy. It's never easy. Lots of digging here and filling back in
there. Splicing pieces, adding turns, corners and making sure it all
heads downhill.
Next was to cover it with gravel, then cover it with a fabric to prevent
soil from filling up the pipe.
Most of the folks I worked with agreed that adding roof drainage away
from the foundation was much better than the roof drainage to splash blocks
that I had on the building plans. Splash blocks would work fine.
However, the water would hit the splash block then just end up in the yards
directly in front of the house all around the house. I agreed that it
would be an improvement to direct the water out just as the foundation
footing drain. The added cost was about $100.00 more and If I did all
the labor it would be pretty cheap. So, I "hung" another pipe from the
sill wall just below where grade would be and directed it all around the
perimeter wall headed downhill just as the footing drain. Only this
pipe was solid, no perforation, it was white #35 pvc pipe and I also had to
glue together joints for all the corners as well as adding 'T' fittings to
run up the wall just above grade so the roof vent could be directed into it.
I was instructed to direct the exit end of this roof drainage pipe into the
same drain line exit run used for the footing drain. |

Shows white roofing drainpipe joining footing drain & shows sewer pipe
cleanout.

Shows drainage heading out into the yard and sewer drainage line to the
septic.

My best buddy, my lil' Toyota pickup. Helper springs, 6 ply tires and a
rack. This lil' gal hauls more than your average little truck by gawd. |
It was fiddly working with the 2 different types of pipe and
hanging it, gluing and making it all go downhill to the same spot was a
little tricky. But, Done. On Inspection day I was at work, so the
inspector didn't have anyone to talk with when he came, and I failed the
inspection. His notes were a little strange:
- Do not connect footing & downspout drains
- Downspouts to be to splash blocks on engineered design for
infiltration trench
- Remove foundation vent covers
- The foundation needs to be vented 1' vent to 150sq'
Well,
my builder consultant always connects the roof drain to the footing drain,
so I had to call about that.
#2 was a statement, and I did call for splash blocks on the plans, not piped
drainage.
Well, as you can see by the picture, I had to tear out the roof drainage I
worked so hard on. Lost $150. and many hours of installation time.
Damn.
#3 was odd, the vents were sold with little doors that open or close and the
inspector wants me to "remove" the doors so the crawlspace is permanently
vented.
#4 just states the number of vents, which I do have so I'm not sure why he
bothered noting that. I found out he measures the actual vent netting
size to get the correct number of sq. inchs per crawl space area. I
was short less than 1 foot of vent space.
The inspector said he didn't know what I was going to do about the venting,
since, the cement has been poured. I'm perplexed as to what the hell I
can do. All my consultants say he should have inspected for venting at
the foundation inspection when I could have fixed it, not after the concrete
is poured. Not sure what to do with this yet. Stay tuned.
Another thing I had to do was lay the septic drain pipe from the septic
to the house. Well, the existing pipe from the trailer to the tank was
very poorly done and used the wrong type of pipe. I laid 55' of
expensive #40 ABS Black DWV pipe from the tank to the new foundation.
I also had to plumb the old trailer pipe into this new pipe until the house
was built. I had to do hours and hours of work digging - filling -
adjusting the critical pipe height in this trench. |