Second Floor
Home BACK

Stairs - Interior Walls - Protective Cover - Sing Log Walls

It's August 27th 2004.  It may be difficult to get the roof on before the weather turns.  We are just barely on the second floor, yet to lay a log.  Fall is around the corner and winter weather typically comes in mid Sept and no later than October.  Got to get the roof on and protection for the building before the big weather change.

The second floor deck is down.  Greg and I got it done in 1 and 1/2 days.  3/4" T&G plywood that is visible from the 1st floor in the living room and spare bedroom.

Interior walls are erected.  Greg and I got these done in about 7 hours.  The whole plan was to get these interior walls up before the rains came.  I needed the walls to hold up the tarp covering the project.
Tarp is covering the project ( Literally - just moments before the rains started!).  Our timing couldn't have been closer.
Lower electrical receptacles are installed on the exterior Sing Logs.  These went pretty fast - I just hope they all work!
Today Sunday the 29th of August I got to the 4th log high on the second floor.  Everything seems to be going much faster than on the 1st floor.  My target is October to get the roof on.  Once that roof is on I will be able to relax allot and not have to constantly worry about the wind and the rain.  The weather has been a major obstacle for this project.  The roof will control all that and the finish work can proceed without much weather problems.

 

Email to:  Dulane or Roy - Remove *** from address - Copy/Paste into your email program:  ***webmaster@spiderhollow.com***
SpiderHollow Sing Log Building project:
 Lot purchase '97.  Permitted 8/20/03 Ground breaking 8/30/03 Move in 9/20/05